# Early Build Team - Sequence - 2025 We have a big build team this year so we're going to split into three groups
Leonardos | Donatellos | Michaelangelos | |
Arrival | Wait for placement | Wait for placement | Make breakfast |
After Placement | Survey and mark locations for Peik deliveries. Call Peik. | Survey and mark fire lane, then locations for fire lane-adjacent deliveries. Call for Empire, Water, Generator | |
After Deliveries | First six tarps | Follow Leonardos building sticks for initial outpost | Hang up and light Turtle Event sign Follow Donatellos adding tarps to sticks |
Follow Michaelangelos to setup first 6 shiftpods | Make dinner | ||
personal setup and dinner done for the night | personal setup and dinner done for the night | personal setup and dinner done for the night | |
Continue laying down tarps | Follow Leonardos building sticks | **Pavillion** Measure and survey Assemble mast on ground When mast is assembled, **all hands** to raise it and secure guylines | |
Follow Donatellos adding tarps to sticks | Follow Leonardos setting up Shiftpods | Anchor all the sails and perfect | |
dinner and done for the night | dinner and done for the night | dinner and done for the night | |
Electrical grid | Water setup | Utility Lighting | |
Dining Room Furnishings | Lotus Belle Tent and its Furnishings | Lounge and Kink Fort Furnishings | |
dinner and done for the night | dinner and done for the night | dinner and done for the night | |
DJ / Audio Gear | DMX Lighting | Pillow Fort Setup | |