Early Build Team - Sequence - 2025

We have a big build team this year so we're going to split into three groups


Leonardos Donatellos Michaelangelos
Arrival Wait for placement Wait for placement Make breakfast
After Placement Survey and mark locations for Peik deliveries.

Call for Empire deliveries.

Survey and mark fire lane, then locations for fire lane-adjacent deliveries.


Call for Empire, Water, Generator 


After Deliveries  First six tarps Follow Leonardos building sticks for initial outpost Hang up and light Turtle Event sign

Follow Donatellos adding tarps to sticks
  Follow Michaelangelos to setup first 6 shiftpods Make dinner

personal setup and dinner

done for the night

personal setup and dinner

done for the night

personal setup and dinner

done for the night






Continue laying down tarps

Follow Leonardos building sticks

Pavillion

Measure and survey

 

Assemble mast on ground

 

When mast is assembled, all hands to raise it and secure guylines


Follow Donatellos adding tarps to sticks

Follow Leonardos setting up Shiftpods

Anchor all the sails and perfect


dinner and done for the night

dinner and done for the night

dinner and done for the night






Electrical grid 

Water setup 

Utility Lighting


Dining Room Furnishings

Lotus Belle Tent and its Furnishings

Lounge and Kink Fort Furnishings


DJ / Audio Gear

DMX Lighting

Pillow Fort Setup