Early Build Team - Sequence - 2025
We have a big build team this year so we're going to split into three groups!
| Leonardos | Donatellos | Michaelangelos | |
| Arrival | Wait for placement | Wait for placement | Make breakfast |
| After Placement |
Survey
Call |
Survey for Empire Deliveries
Measure and mark fire
Sierra Site Svcs 888-458-8777 Generator World 916-668-0605 |
|
| After Deliveries | First six tarps | Follow Leonardos building sticks for initial outpost | Hang up and light Turtle Event sign Follow Donatellos adding tarps to sticks |
| Follow Michaelangelos to setup first 6 shiftpods | Make dinner | ||
|
personal setup and dinner done for the night |
personal setup and dinner done for the night |
personal setup and dinner done for the night |
|
|
Continue laying down tarps |
Follow Leonardos building sticks |
Pavillion
Assemble mast on ground
When mast is assembled, all hands to raise it and secure guylines |
|
|
Follow Donatellos adding tarps to sticks |
Follow Leonardos setting up Shiftpods |
Anchor all the sails and perfect |
|
|
dinner and done for the night |
dinner and done for the night |
dinner and done for the night |
|
|
|
|
|
|
|
Electrical grid |
Water setup |
Utility Lighting |
|
|
Dining Room Furnishings |
Lotus Belle Tent and its Furnishings |
Lounge and Kink Fort Furnishings |
|
|
dinner and done for the night |
dinner and done for the night |
dinner and done for the night |
|
|
|
|
|
|
|
DJ / Audio Gear |
Light whips and bike parking |
Pillow Fort Setup |
|
|
DMX Lighting |
|
|