Skip to main content

2025 Gayflower Wish List

IMG_1366.jpg

Introduction

After two years in operation we have a wish list for some improvements and repairs that could be made to the Gayflower. These would have to be done in Empire, NV in the spring.

Priority
Project
Status
5 Urgent
Fix Leaks Around Fresh Water Pump
The main green fresh water pump has a few little drips. There is a second leak on the thin brass fitting where water goes off to the swamp cooler.

5 Urgent
Replace IBC Totes With New
The four IBC totes in the back were used for fruit juice concentrate and cause the water to smell poorly.
One of the three IBC totes in the front (the rearmost one) has a broken shutoff valve.

5 Urgent

Seal Waste Line at Second Urinal

We haven't been able to use the second urinal because the waste line leaks.


3 Medium

Leaks around sink bases


5 Urgent

Leak in Grey Water Connecting Hoses

The one we noticed was probably the rearmost, passenger-side grey water holding tank.

4 Important

Steel Support For IBC Totes in Back

Weld in place a steel structure to support the weight of the water tanks in back

4 Important

Bathtub / Secondary Containment for Grey / Black Water Tanks
There is an interesting problem that if the grey or black water tanks leak or the hoses connecting them come apart, the contents go onto the playa.
At the very least it seems like it should be possible to shut off any single waste water tank at the fitting in case the leak is downstream of that. Maybe then there could be a way to pump its contents into another tank?


4 Important

Level Indicators for Waste Water Tanks
Apparently there are already sensors connected to the grey and black water tanks to measure the level, but they are not hooked up to anything that can be used to read their output.